Hello all. I am looking to get an answer on the XViz Gantt visual.
I have two different reports for two different departments that I am trying to visualize, however I am using the XViz Gantt for both reports. One of the reports shows my progress value go past the goal when it my progress is over my progress base, however, my other report does not show this. I would like the progress to "shoot past" the end of the gantt bar when I achieve this. (Shown on the -827 line). Is there a setting for this?
Let me know.
Thanks!
Jon
One, shows when there is