Hello,

I have a few functions I’m looking to do but can’t seem to get them to visualize:

  1. Minimize the categories and remove the option to expand. I ultimately want to have 1 row for each projects, with progress and milestones populated.
  2. When minimized, the tooltip only shows the progress of the overall task/project. Can it be enabled to show the milestone when moused over?

Here’s my current view:

Data is coming from Project Online.

TIA,

Trent

Answered question
0

1.Only Assing Project to the taskName.Also, make sure taskName is not repeated.
2 a. Then you can assign milestone what you want to show to the milestone Field.
b. Chose Display as Marker in Milestone Tab of AdvanceEditor(you can go to advance editor by click pencil symbol appears on visual)

Answered question