Gantt Chart Progress
Hi
In the Gantt Chart, for the Progress indicator we have a value of 0 through 100. Yet on the Gantt chart it shows up as 1.00% for every task. What format does the data need to be for the Progress indicator to work? We’ve put in both Start and End Dates and that part is working.
Thanks!
Question is closed for new answers.
Dharani Selected answer as best
Hi,
The Progress indicator value should be in the numeric or percentage format. This will automatically show the value as percentage in the Gantt chart.
Dharani Selected answer as best


I’ve set the ‘Min of …’ for another report and worked. May you try?
In my case the data source (both in the desktop and online app) has 75% informed but the visualisation paints a 7500% and so does the Tooltip.
Thanks. On ours it says that Progress = Count of Percent Complete. Is that right? If not, then perhaps that is why everything shows up as Progress = 1.00%