Gantt Chart Progress
Hi
In the Gantt Chart, for the Progress indicator we have a value of 0 through 100. Yet on the Gantt chart it shows up as 1.00% for every task. What format does the data need to be for the Progress indicator to work? We’ve put in both Start and End Dates and that part is working.
Thanks!
Niveda Murali Answered question
Thanks. On ours it says that Progress = Count of Percent Complete. Is that right? If not, then perhaps that is why everything shows up as Progress = 1.00%