In the feature description for the Gantt Chart, it states that Timelines can be customized. Is there a way to specify what the “top level”, “Mid level” or “Low level” should be? Specifically I need to always view the year and week number, and it looks in the feature description like it should be possible.

Answered question
0

That option is under advance editor, you can access the advance editor by clicking the highlighted icon in the image.

Answered question
0

yes, it is possible with the latest Gantt version.you can download the latest version
from our website.

Then configure zoom levels as above, and turn off the middle level of the timeline.

Edited comment

Hi Thor. Thank you very much for your answer! I am not seeing the option that you are describing. I just downloaded the version from the website v.1.1.3.

When I search “Zoom” in the formatting settings, I only get the “Zoom button” or “Zoom range Enable”