How to customize gantt chart timelines

1.76K viewsDate gantt-chart Timeline
0

In the feature description for the Gantt Chart, it states that Timelines can be customized. Is there a way to specify what the “top level”, “Mid level” or “Low level” should be? Specifically I need to always view the year and week number, and it looks in the feature description like it should be possible.

Answered question
0

That option is under advance editor, you can access the advance editor by clicking the highlighted icon in the image.

Answered question
You are viewing 1 out of 2 answers, click here to view all answers.