Milestones with their own percent complete not sum grouped under a project
Hi by putting the projectname and taskname in the taskname field I can get a grouping
however putting percent complete in the progress field just allows sum, max etc. I want what the %complete is for that milestone not an aggregate.
how can I do this?
Question is closed for new answers.
Prachi Selected answer as best
Hello Rayletts,
In the below image, I have displayed the progress %completed for the givens tasks and I have a hierarchy in place.
The progress % for the task i.e., the projectname is calculated only by taking the aggregation of its sub tasks, whereas the given progress% is taken for the sub tasks.
Prachi Selected answer as best